Skip Navigation

how long?

Started by bb10024
over 15 years ago
Posts: 164
Member since: Dec 2008
Discussion about
once i get board approval.. how much time should i assume and full kitchen and bath renovations should take? i was thinking 6weeks
Response by Primer05
over 15 years ago
Posts: 2103
Member since: Jul 2009

It depends on what you are doing, if they are both full guts then I would think a little longer to be on the safe side about 8 weeks.

You have to order the cabinets then once they are installed the marble/granite fabricator needs to do a template and then it could take two weeks just for that. It depends on how much plumbing you are doing as well, you might need a building shut down, that could take a couple of days to get the notices out.

Ignored comment. Unhide
Response by romary
over 15 years ago
Posts: 443
Member since: Aug 2008

6 weeks? u jest. plan on 3 months so you won't be disappointed.

Ignored comment. Unhide

Add Your Comment