negotiating additional amenities/ fixtures on new condos

Started by nyc08
over 18 years ago
Posts: 74
Member since: Feb 2008
Discussion about
i've been looking at some of the new condo developments in brooklyn which are almost but not quite completed and i was wondering if it's possible to negotiate additional amenities/ fixtures as part of the offer. for example, some of the units i've been looking for have 1/2 baths and i would like to add a shower or bathtub and make a full bath since the floorplan would has anyone ever done this? if so, does anyone have any idea how much would something like this (adding a shower/bathtub to a half bathroom) cost? thanks!
Response by nyc08
over 18 years ago
Posts: 74
Member since: Feb 2008

correction to above:
i would like to add a shower or bathtub and make a full bath since the floorplan would allow for this (space-wise). has anyone ever done this?

if so, does anyone have any idea how much would something like this (adding a shower/bathtub to a half bathroom) cost?

Ignored comment. Unhide
Response by greeny
over 18 years ago
Posts: 19
Member since: Feb 2008

not all new construction will allow you to make any modifications. i inquired about some simple changes (ie an additional shower head, change of faucet) as well as an upgraded tub to jetted and was told no on everything. They said all modifications had to be done post closing due to offering plan, insurance, etc etc etc. Which kinda defeated the purpose of wanting the changes made before the walls were up and bathroom completed...

Ignored comment. Unhide
Response by nyc08
over 18 years ago
Posts: 74
Member since: Feb 2008

interesting greeny. if the developer didn't agree to do the modifications i would probably move on to the next property... in your case, were they willing to do the changes after the closing or would you have to get an outside contractor on your own? my concern there would be getting the same materials so that the bathroom would match (i.e., add'l tiles, shower heads, faucets, etc.) such a pain!

Ignored comment. Unhide
Response by malraux
over 18 years ago
Posts: 809
Member since: Dec 2007

The issue is different than you think.

In a modest to large sized new condo build (let's assume 50 units or more), the builder has an outstanding construction loan racking up interest every day from day one until they close and get paid by the unit owners. Therefore, the builder/sponsor has real incentive to build and close as quickly as possible to increase their profit margin, and delays mean lost money. If you want a 'little change' in your unit, and you were the ONLY person, it would be no big deal. But if they do it for you, they have to do 'little changes' for everyone, which means a massive amount of extra work and extra time, which mean lost $'s.

In a smaller new high end build like the one I moved into (sub 15 units), the builders are sometimes more amenable to changes as long as they're not backbreaking.

Ignored comment. Unhide
Response by greeny
over 18 years ago
Posts: 19
Member since: Feb 2008

mine was <50 units and they said everything would have to be done post closing and hiring our own people.

Ignored comment. Unhide
Response by nyc08
over 18 years ago
Posts: 74
Member since: Feb 2008

thanks for the explanation malraux, i guess i'll ask and see what their response is... do you have any idea hw much something like this would cost $$-wise? so i can factor this into my offer...

Ignored comment. Unhide
Response by nyc08
over 18 years ago
Posts: 74
Member since: Feb 2008

that's too bad greeny. did you walk?

Ignored comment. Unhide